Disannex
requests OK'd by board
By Andrew Steele
Star Managing Editor
CROWN POINT - Five individual properties and the
Miller's Farm subdivision were disannexed from the city Monday at the
request of the property owners.
The disannexations were approved by the Board of
Public Works in accordance with an agreement between the city and
property owners on the east side of the 6.5-square-mile annexation
surrounding the I-65 and U.S. 231 intersection.
Among the properties disannexed was the Hein family
dairy farm.
Vern Hein said that "we have no animosity toward
... the city of Crown Point" but that "we think the annexation
of our farmland was maybe a little premature."
Perhaps in five years, he said, "we might be
trying to get into the city."
Mayor James Metros said the disannexations are consistent with the
city's plans for the area.
One concern, though, was raised by a resident of East 121st Avenue, who
noted that a portion of her street would now be in the county's
jurisdiction.
City Engineer Jeff Ban said plowing and road
maintenance responsibilities are worked out between the county and city.
"We don't want you to think you'll be on an
island all by yourself," Metros said.
Also Monday, the board approved an additional $80,000 for the $2.2
million project to extend sewer and water service to the I-65 and U.S.
231 interchange.
The additional money will be used for underground
boring, Ban said.
Originally, the contractor was to bore 50 feet under
a railroad right-of-way near Delaware Street, but the city has decided
to continue the boring another 150 feet for the sewer main and 235 feet
for the water main in order to minimize damage to other properties on
the utility route.
END
|
School
work gets on track
By Andrew Steele
Star Managing Editor
CROWN POINT - Bad weather in December put work on the
new Crown Point High School three to four weeks behind schedule, project
manager Scott Cherry told the School Board last week, but "we're
positive we can make that up," he said.
Winter weather particularly hurt masonry work, but
Cherry, of Skillman Corp., said that he was optimistic the contractor,
Gough Construction, would be able to make up the time.
"We're hoping to start the (outer) brick work in
a couple weeks, weather permitting," Cherry said at the March 12
board meeting. That will finally "add some color" to the
concrete-gray edifice at Burrell Drive and Main Street.
Meanwhile, work continues on the masonry bearing
walls in the performing arts, athletic and mechanical areas.
The auditorium, fieldhouse, and mechanical rooms are
under roof, and the main gymnasium is partially roofed, Cherry said, and
structural steel is going up in the classroom wing.
Work continues on the athletic fields as well, Cherry
said. Those fields fill the southern end of the school property.
Skillman's schedule for the year includes work on all major parts of the
project.
Mechanical rooms and athletic fields are expected to
be completed this year, while work on the bulk of the building runs to
late 2002 and early 2003.
The building is expected to open to students for the
2003-2004 school year.
The construction cost is currently $58,290,003, down from the original
bid amount of $58,624,878.
The decline is due to minor revisions in the project
and "value engineering" that reduced the amounts in several
areas.
Those savings, less change order expenses already
approved, have been added to the project "contingency fund,"
which is used to pay for change orders.
END
|